Question

A learner is comparing two similar concepts for the PMP Project Management Professional involving servant leadership in Agile and Hybrid Methods. Which answer is best? (Item 103)

Answer choices

  1. A. Choose an answer that removes accountability from the responsible professional.
  2. B. Escalate only after taking irreversible action without reviewing the facts.
  3. C. The best answer is to select the response that protects project value, uses appropriate tailoring, engages stakeholders, and follows ethical project management practice for the servant leadership scenario.
  4. D. Treat all similar terms as interchangeable without checking the scenario context.

Correct Answer

C. The best answer is to select the response that protects project value, uses appropriate tailoring, engages stakeholders, and follows ethical project management practice for the servant leadership scenario.

Explanation

The correct answer is C because servant leadership is tested by asking candidates to select the response that protects project value, uses appropriate tailoring, engages stakeholders, and follows ethical project management practice. The distractors reflect common exam mistakes: ignoring context, using informal shortcuts, skipping verification, or applying a rule from the wrong domain.

Question details

  • Difficulty: medium
  • Domain: Agile and Hybrid Methods
  • Objective: servant leadership