Process and Delivery Practice Question
Question
A practitioner wants to reduce risk before proceeding for the PMP Project Management Professional involving quality management in Process and Delivery. Which answer is best? (Item 168)
Answer choices
- A. Skip verification because the previous case had the same answer.
- B. Document nothing because documentation could create follow-up questions.
- C. Rely on informal custom instead of the applicable rule, control, or standard.
- D. The best answer is to select the response that protects project value, uses appropriate tailoring, engages stakeholders, and follows ethical project management practice for the quality management scenario.
Correct Answer
D. The best answer is to select the response that protects project value, uses appropriate tailoring, engages stakeholders, and follows ethical project management practice for the quality management scenario.
Explanation
The correct answer is D because quality management is tested by asking candidates to select the response that protects project value, uses appropriate tailoring, engages stakeholders, and follows ethical project management practice. The distractors reflect common exam mistakes: ignoring context, using informal shortcuts, skipping verification, or applying a rule from the wrong domain.
Question details
- Difficulty: hard
- Domain: Process and Delivery
- Objective: quality management