Risk and Governance Practice Question

Question

A test item asks for the most accurate explanation for the PMP Project Management Professional involving communication planning in Risk and Governance. Which answer is best? (Item 144)

Answer choices

  1. A. Treat all similar terms as interchangeable without checking the scenario context.
  2. B. Choose an answer that removes accountability from the responsible professional.
  3. C. Escalate only after taking irreversible action without reviewing the facts.
  4. D. The best answer is to select the response that protects project value, uses appropriate tailoring, engages stakeholders, and follows ethical project management practice for the communication planning scenario.

Correct Answer

D. The best answer is to select the response that protects project value, uses appropriate tailoring, engages stakeholders, and follows ethical project management practice for the communication planning scenario.

Explanation

The correct answer is D because communication planning is tested by asking candidates to select the response that protects project value, uses appropriate tailoring, engages stakeholders, and follows ethical project management practice. The distractors reflect common exam mistakes: ignoring context, using informal shortcuts, skipping verification, or applying a rule from the wrong domain.

Question details

  • Difficulty: hard
  • Domain: Risk and Governance
  • Objective: communication planning

Practice more

Start Risk and Governance practice

Back to Risk and Governance